Ralph L. Wadsworth Construction Company, LLC v. Regional Rail Partners; Balfour Beatty Infrastructure, Inc.; Graham Contracting Ltd.; Travelers Casualty and Surety Company of America; Balfour Beatty, LLC; and Graham Business Trust
- Decided
- March 24, 2025
- Docket
- 24SC537
- Status
- Unpublished
- Jurisdiction
- Colorado
Cited 0 timesNo negative treatment found in this library
What does the opinion say?
[1]
Ralph L. Wadsworth Construction Company, LLC, Petitioner v. Regional Rail Partners; Balfour Beatty Infrastructure, Inc.; Graham Contracting Ltd.; Travelers Casualty and Surety Company of America; Balfour Beatty, LLC; and Graham Business Trust, Respondents No. 24SC537 Supreme Court of Colorado, En Banc March 24, 2025 Petition for Writ of Certiorari GRANTED.
Whether a claimant who files an excessive verified statement of claim under the Colorado Public Works Act, §§ 38-26-101 to -110, C.R.S. (2024), forfeits both its statutory remedies and all other available legal remedies or, as with an excessive lien claimant under the General Mechanics' Lien Act, forfeits its statutory remedies only.
Whether a verified statement of claim under the Colorado Public Works Act may lawfully include disputed amounts, such as additional costs incurred by a subcontractor due to project delays and disruptions, or whether such claims are limited to undisputed, liquidated amounts.
Cite this
Ralph L. Wadsworth Construction Company, LLC v. Regional Rail Partners; Balfour Beatty Infrastructure, Inc.; Graham Contracting Ltd.; Travelers Casualty and Surety Company of America; Balfour Beatty, LLC; and Graham Business Trust, No. 24SC537 (Supreme Court of Colorado March 24, 2025)No reporter citation is stored for this case. This line is built from the stored case name, docket number, court and decision date.