1 IN THE UNITED STATES BANKRUPTCY COURT 2 FOR THE DISTRICT OF PUERTO RICO 3 IN RE: CASE NO. 02-02887(ESL) 4 REDONDO CONSTRUCTION CHAPTER 11 CORPORATION 5 6 Debtor REDONDO CONSTRUCTION ADV. PROC. NO. 03-00192 (ESL) 7 CORPORATION ADV. PROC. NO. 03-00194 (ESL) ADV. PROC. NO. 03-00195 (ESL) 8 Plaintiff 9 vs. 10 PUERTO RICO HIGHWAY AND 11 TRANSPORTATION AUTHORITY 12 Defendant 13 OPINION AND ORDER 14 15 These adversary proceedings are before the court upon the Brief as to [] Extended Home 16 Office Overhead Damages filed by Plaintiff Redondo Construction Corp. (“Redondo”) (Adv. 17 Proc. No. 03-00192 Docket No. 333, Adv. Proc. No. 03-00194 Docket No. 293 and Adv. Proc. 18 No. 03-00195 Docket No. 265). Each adversary proceeding corresponds to a different project 19 where Redondo intervened as a contractor: Adv. Proc. No. 03-00192 corresponds to project 20 Desvío Sur de Patillas (“Desvío Sur de Patillas”), Adv. Proc. No. 03-00194 corresponds to PR 2 21 Mayaguez (“PR 2 Mayaguez”), and Adv. Proc. No. 03-00195 corresponds to Dorado-Toa Alta 22 (“Dorado-Toa Alta”). Also before the court is Puerto Rico Highway and Transportation 23 Authority’s (“PRHTA”) Brief on the home-office overhead damages, but only in regards to the 24 PR 2 Mayaguez Project (Adv. Proc. No. 03-00194 Docket No. 209). PRHTA did not file briefs 25 in Adv. Proc. Nos. 03-00192 and 03-00195. For the reasons stated below, Redondo’s claims for 26 home-office overhead damages are only allowed under the percentage-of-direct-costs approach. 27 1 Procedural Background 2 On January 13, 2014, this court entered an Opinion and Order (Lamoutte. B.J.) in the 3 instant adversary proceedings granting Redondo pre-judgment interest at six percent (6%) under 4 Article 1061 of the Civil Code of Puerto Rico, 31 L.P.R.A. § 3025, with an accrual period 5 starting from the stipulated dates of substantial completion until PRHTA’s final payment on the 6 principal of the principal amounts for each project. In regards to the home-office overhead 7 damages, the court ordered as follows:

8 Because the Joint Stipulations filed by the parties do not address whether the extra 9 work performed by Redondo in the three projects were the result of “necessary but unanticipated work” or whether the delay did not arise from a need to perform extra 10 work as mandated by the [Court of Appeals for the] First Circuit [the “First Circuit”], the court orders the parties to file additional stipulations to that effect or 11 separate briefs making specific references to the evidence submitted during the trial to that effect and attaching copies of the same. 12 13 If the extra work performed by Redondo in the three projects was the result of “necessary but unanticipated work” and the percentage-of-direct-costs method is 14 applicable, the parties shall stipulate and/or brief the court on the percentage to be applied to the corresponding costs (via change orders and/or extra work orders) 15 making specific references to the evidence submitted during the trial to that effect and attaching copies of the same. 16 17 If the Eichleay[1] formula is to be applied, the court further orders the parties to stipulate the calculation of such damages and/or file separate briefs that include 18 specific references to the evidence submitted during the trial to that effect and attaching copies of the same. 19 20 See Adv. Proc. No. 03-00192 Docket No. 321, Adv. Proc. No. 03-00194 Docket No. 282 and 21 Adv. Proc. No. 03-00195 Docket No. 279. The Opinion and Order (Lamoutte, B.J.) is 22 published at 505 B.R. 388 (Bankr. D.P.R. 2014) and contains a detailed procedural background 23 of these adversary proceedings. The court granted the parties thirty (30) days to file the joint 24 stipulations or briefs on the issue of home-office overhead damages. 25 26 27 1 The Eichleay formula is the one established in In re Eichleay Corp., 1960 ASBCA Lexis 1207, 1960 WL 538 1 On February 12, 2014, PRHTA filed its Brief in compliance with the Opinion and Order 2 for the PR 2 Mayaguez Project. See Adv. Proc. 03-00194 Docket No. 290. It did not file a 3 brief for the other two projects (Adv. Proc. Nos. 03-00192 and 03-00195) claiming that it “was 4 [not] able to prepare [them] within the strict time constraints set by the [] court” (Adv. Proc. 03- 5 00194 Docket No. 307, p. 5, ¶ 16). PRHTA did not request an extension of time to file such 6 briefs in those adversary proceedings. In its only Brief, PRHTA sustains that the extra work 7 performed in the PR 2 Mayaguez Project was the result of 39 change orders and 32 extra work 8 orders agreed by the parties, and therefore, Redondo has already been compensated for home- 9 office overhead damages through the direct-cost method, which excludes Eichleay damages 10 according to the parameters established by the First Circuit. In addition, PRHTA avers that 11 there is no evidence that Redondo was stopped (totally or partially) from construction or that it 12 was put in any kind of standby during the completion of additional work performed for the PR 2 13 Mayaguez Project. 14 On February 14, 2014, Redondo filed a consolidated Brief for all three projects in each 15 of the instant adversary proceedings. See Adv. Proc. No. 03-00192 Docket No. 333, Adv. Proc. 16 No. 03-00194 Docket No. 293 and Adv. Proc. No. 03-00195 Docket No. 265. Redondo’s Brief 17 offers a lengthy description of the problems and mishaps it confronted during the construction 18 of each project. Regarding the Desvío Sur de Patillas Project, Redondo contends that “some of 19 the problems [it] experienced [] consisted of an under-run in the installation of the piles, with 20 the surveying, the elevation of the decks, and design problems, such as the diaphragms and the 21 beams” (Adv. Proc. 03-00192 Docket No. 333, p. 22, ¶ 68). Redondo further stated that it had 22 to submit “a revised claim to the PRHTA for $34,072.27 for the unrecovered expenses.” Id. at 23 p. 24, ¶ 74. Redondo also submitted its final claim on February 21, 1995 to PRHTA “including 24 the under-run on the piles and the additional expenses incurred in the construction ... as 25 evidenced by 15 change orders and 22 extra work orders .... [s]aid Claim includes a net 26 $254,252.36, plus a 10% profit factor of extended home-office overhead.” Id. at p. 24, ¶ 75. 27 Redondo also notified the PRHTA of all the problems related to the worksite and admits that the 1 site condition “could not be predetermined prior to perfuming the activity” and that at the end of 2 the activity it would submit a request for payment. Id. at p. 25, ¶ 80. 3 For the Dorado-Toa Alta Project, Redondo sustains that the major problem was the “de- 4 watering problem in building the pier” (Adv. Pr. 03-00195 Docket No. 288, p. 26, ¶ 84). 5 Redondo avers that it relied on the information provided by PRHTA and did not inspect the job 6 site before placing a bid for it. Id. at p. 28, ¶ 96. Upon realizing the actual site conditions of the 7 project, Redondo hired a consultant to evaluate the situation. Id. at p. 28-29. Redondo 8 ultimately submitted a “claim for extended home-office overheard for $23,814.00 plus 10% 9 profit factor ... following the Eichleay formula.” Id. at pp. 29-30, ¶ 106. 10 For the PR 2 Mayaguez Project, Redondo acknowledges that “[t]he required change 11 order and extra work orders were of such magnitude that the PRHTA agreed to extensions of 12 almost three (3) times of the original contract time” (Adv. Pro. 03-00194, Docket No. 293, p. 13 15, ¶ 36). According to Redondo, the cause of the change orders and extra work orders, 14 included: incomplete technical plans, insufficient technical information provided by PRHTA, 15 and that the original plans did not comply with certain requirements set forth by other 16 government agencies and differences in the terrain. Id. at 15, ¶ 38. Redondo asserts it had to 17 subcontract Continental Lord, Inc. (“Lord”) to perform the electrical work on this project. Id. at 18 p. 16, ¶ 39. Redondo asseverates that “Lord was delayed approximately 453 days” by PRHTA 19 and “was directed to stop[2] its work as to this activity when the problem [with the installation 20 of the light post] arose until it was solved.” Id. at p. 17, ¶ 42, and p. 18, ¶ 47. The stoppage was 21 caused by a need to redesign some light poles at the behest of PRHTA. Id. Afterwards 22 Redondo submitted to the PRHTA “32 extra work orders for around $2M” for “90 activities not 23 contemplated in the original plans and specifications.” Id. at p. 20, ¶ 59. 24 Finally, Redondo proposes that all the change orders and extra work orders in the 25 projects constitute ‘extinctive novations’ and that PRHTA is now bound by them. Id. at p. 32, ¶ 26 115. Redondo contends that the “unforeseen extraordinary and unreasonable delay are not only 27 1 premised [] on the multiple change and extra work orders, but also on the extraordinary 2 circumstances occurring [sic] during the performance of the contracts.” Id. at p. 35, ¶ 125. 3 Redondo claims that the percentage of direct-cost-method is inapplicable in the instant case and 4 that all the unforeseen extraordinary and unreasonable delay caused them to be on standby. 5 Therefore, Redondo concludes that the Eichleay requirements have been met, which entitles it 6 to be compensated for Eichleay damages. 7 Applicable Law & Analysis 8 (A) Forfeiture of Claims and the “Law of the Case” Doctrine 9 The First Circuit has ruled that “[a] party waives a right only if he intentionally 10 relinquishes or abandons it; he forfeits a right by failing to assert it in a timely manner.” Dávila 11 v. Corporación de Puerto Rico para la Difusión Pública, 498 F.3d 9, 15 (1st Cir. 2007). A 12 “waiver is different from forfeiture”. U.S. v. Mangone, 105 F.3d 29, 35 (1st Cir. 1997). 13 “Forfeiture is the failure to make the timely assertion of a right, waiver is the ‘intentional 14 relinquishment or abandonment of a known right.’” U.S. v. Olano, 507 U.S. 725, 732 (1993), 15 quoting Johnson v. Zerbst, 304 U.S. 458, 464 (1938). Moreover, even constitutional rights may 16 be forfeited in criminal and civil cases “by failure to make a timely assertion of the right before 17 a tribunal having jurisdiction to determine it”. U.S. v. Olano, 507 U.S. at 731 . 18 In the instant case, the court cannot find on the record any “extinctive novation” 19 pleading or argument made by Redondo prior to the filing of its Brief. On the contrary, the 20 court finds that such argument was made for the first time by Redondo at this advanced stage of 21 the proceedings, that is, after the Judgment & Mandate issued by the First Circuit and the 22 Mandate issued by the U.S. District Court for the District of Puerto Rico remanding these cases 23 to this court for further proceedings consistent with the First Circuit’s ruling. Furthermore, the 24 First Circuit’s instructions did not include any parameters on “extinctive novation” for this 25 court’s consideration. Therefore, the court deems Redondo’s “extinctive novation” arguments 26 forfeited. The court will strictly adhere to the First Circuit’s remanded instructions, which now 27 constitute the “law of the case”. 1 (B) Extended Overhead Damages 2 The First Circuit’s remand instructions to this court are the following:

3 In the case[s] at hand, the bankruptcy court employed Eichleay to calculate 4 [Redondo’s] extended overhead damages. See Redondo, 411 B.R. 89 , 95 and 108 (Bankr. D.P.R. 2009). But the court mixed apples and oranges; it used Eichleay 5 across the board even though it found that at least some of the project delays were attributable to extra work for which the debtor was compensated. See, e.g., id. at 6 95, 97, 104-05. For those delays, extended overhead should have been awarded as a percentage of the direct costs associated with the projects’ change orders and 7 extra work orders. See C.B.C. Enters., Inc. v. U.S., 978 F.2d 669, 675 (Fed. Cir. 8 1992) (“[I]t is inappropriate to use the Eichleay formula to calculate home-office overhead for contract extensions because adequate compensation for overhead 9 expenses may usually be calculated more precisely using a fixed percentage formula.”). 10 ... On remand, the bankruptcy court is free to determine whether the debtor sustained 11 uncompensated periods of delay and, if so, whether Eichleay damages are 12 appropriate for any such periods. In resolving this issue, the court should address the [PRHTA]’s argument that Federal Circuit precedent bars Eichleay damages 13 here because work on the three projects was never fully suspended. See P.J. Dick Inc. v. Principi, 324 F.3d 1364, 1371 (Fed. Cir. 2003). 14 In re Redondo, 678 F.3d at 124-125 (footnote omitted). 15 16 The Opinion and Order (Lamoutte, B.J.) entered by this court on January 13, 2014 17 applied the First Circuit’s parameters and legal framework under which overhead damages 18 would be considered: 19 The First Circuit defined “extended overhead damages” as those that “compensate 20 a contractor for unabsorbed home-office expenses that accrue during a delay caused by the owner.” In re Redondo, 678 F.3d 115 , 123 (1st Cir. 2012). 21 “Overhead is commonly defined as those costs which are expended for the benefit of the business as a whole and which usually accrue over time ... overhead costs 22 are therefore not directly attributable to specific contracts, for if they were, they 23 would constitute direct costs.” Aircraft Gear Corporation v. Kaman Aerospace Corporation, 875 F.Supp. 485, 495 (N.D. Ill. 1995). Also see Southwestern 24 Engineering Co. v. Cajun, 915 F.2d 972, 978 (5th Cir.1990) (“extended overhead is a concept unique to construction contracting and is defined as the additional 25 costs incurred when a job’s performance period is prolonged”). ... 26 To calculate an award for extended overhead damages, the First Circuit 27 distinguished between (a) projects where the delay is due to “necessary but unanticipated work” and (b) projects where the delay does not arise from a need to perform extra work. In re Redondo, 678 F.3d at 124. When a project is 1 delayed due to “necessary but unanticipated work” for which the contractor is 2 entitled to compensation, extended overhead is calculated as a percentage of the direct costs of the additional work. “This percentage-of-direct-costs approach 3 comports with standard practice in the construction industry under which a contractor normally charges an owner a percentage of a project's direct costs to 4 cover its overhead.” Id. at 124. Conversely, when a project's delay does not arise from a need to perform extra work, for instance, when the owner causes a total 5 work stoppage, the percentage-of-costs approach would deny the contractor any 6 overhead damages for the delay period. Id. In those instances, courts use the Eichleay formula, which “calls for multiplying the average daily overhead costs 7 allocable to a project by the number of days that the project is delayed.” Id. 8 In re Redondo, 505 B.R. at 402-403 . 9 Thus, this court condensed the First Circuit’s mandate into the following query:

10 The mandated task of this court is to find whether the delays in the three projects were due to “necessary but unanticipated work” (to which the court must apply 11 the percentage-of-direct-costs approach) or whether the delay did not arise from a 12 need to perform extra work (to which the court must apply the Eichleay formula). The query further translates into finding if Redondo was compensated for the 13 extra work performed caused by the delay. See In re Redondo, 678 F.3d at 124. If the extra work was compensated, then “the extended overhead should [be] 14 awarded as a percentage of the direct costs associated with the projects’ change orders and extra work orders”. 15 16 In re Redondo, 505 B.R at 403. Upon the foregoing query, the court stated: 17 18 Because the Joint Stipulations filed by the parties do not address whether the extra work performed by Redondo in the three projects were the result of 19 “necessary but unanticipated work” or whether the delay did not arise from a need to perform extra work as mandated by the First Circuit, the court orders the 20 parties to file additional stipulations to that effect or separate briefs making 21 specific references to the evidence submitted during the trial to that effect and attaching copies of the same. 22 If the extra work performed by Redondo in the three projects was the result of 23 “necessary but unanticipated work” and the percentage-of-direct-costs method is applicable, the parties shall stipulate and/or brief the court on the percentage to be 24 applied to the corresponding costs (via change orders and/or extra work orders) 25 making specific references to the evidence submitted during the trial to that effect and attaching copies of the same. 26 If the Eichleay formula is to be applied, the court further orders the parties to 27 stipulate the calculation of such damages and/or file separate briefs that include specific references to the evidence submitted during the trial to that effect and 1 attaching copies of the same. 2 In re Redondo, 505 B.R. at 408 (footnote omitted). 3 4 Redondo’s own Brief reveals that although the three Projects faced considerable delays 5 and unexpected work, they were processed with PRHTA through extra work orders and/or 6 change orders. See Adv. Proc. 03-00192 Docket No. 333, p. 24, ¶ 75; Adv. Pr. 03-00195 7 Docket No. 288, p. 29-30, ¶ 106; Adv. Pro. 03-00194 Docket No. 293, p. 15, ¶ 36. In these 8 adversary proceedings, the First Circuit ruled that when delays in a project are attributable to 9 extra work performed, then the “extended overhead should [be] awarded as a percentage of the 10 direct costs associated with the projects’ change orders and extra work orders.” In re Redondo, 11 678 F.3d at 124. The court rejects Redondo’s contention that the percentage-of-direct-costs 12 method is inapplicable to these adversary proceedings, especially when it acknowledged in its 13 Brief that the delays were attributable to necessary extra work and it submitted claims for 14 payment on all that extra work through change orders and extra work orders. Following the 15 First Circuit’s mandate, this court finds that the Eichleay formula is inapplicable to any of the 16 projects in the three adversary proceedings. 17 Although Redondo vaguely mentions that its subcontractor Lord --not Redondo itself-- 18 was delayed while the project was being re-designed, Redondo only references as evidence the 19 transcript of a hearing held on February 26, 2007. Upon the examination of that transcript and 20 the testimony of Mr. Angel Mercado from Lord, it is clear to the court that although he had to 21 change the entire electrical design of the light post at the behest of PRHTA, Lord’s proposal to 22 make the required changes was approved through extra work orders for that type of work (Adv. 23 Proc. 03-00192 Docket No. 110, p. 143, lines 13-19). Such extra work was unanticipated and 24 necessary, making any claims under the Eichleay formula inapplicable. 25 PRHTA proposes that the percentage-of-direct-costs method must be applied in the 26 instant case because Redondo was already compensated for the home-office overhead through 27 change orders or extra work orders. See Adv. Proc. 03-00194 Docket No. 290, p. 23, ¶ 13. The 1 || only evidence referenced by PRHTA is the transcript and testimony of Architect Redondo, who 2 || stated that “overhead [was] included in the total bid [for the Mayagtiez Project]” (Adv. Proc. 03- 3 ||00192 Docket No. 102, p. 26, lines 20-21). PRHTA did not brief or evidence the inclusion of 4 || overhead in the other projects bids and/or how it compensated Redondo, if at all, for these 5 ||damages. Notwithstanding, pursuant to Redondo’s assertions in its Brief, PRHTA’s argument 6 ||regarding the application of the percentage-of-direct-costs approach holds true for the other 7 || projects in the instant adversary proceedings. 8 Conclusion 9 In view of the foregoing, pursuant to the First Circuit’s rulings and mandate, the court 10 || concludes the Eichleay formula is inapplicable to the instant adversary proceedings. Redondo’s 11 ||claims for home-office overhead damages are only allowed under the percentage-of-direct-costs 12 ||approach. The court orders the parties to file joint or separate motions within 30 days providing 13 ||evidence of how Redondo has already been compensated for overhead damages, if at all, 14 || through the percentage-of-direct-costs approach. If Redondo has not been compensated through 15 ||the percentage-of-direct-costs approach, the parties are hereby ordered to provide the 16 ||calculation of such damages using that approach making specific references to the evidence 17 || submitted during the trial to that effect and attaching copies of the same. Failure to do so as 18 || instructed will result in the court deeming these damages paid and/or forfeited. 19 SO ORDERED. 20 In San Juan, Puerto Rico, this 14" day of July, 2014. 21 73 unitdh states Bankruptcy Judge 24 25 26 27 9.

Cite this

In re: Redondo Construction Corporation v. Puerto Rico Highway and Transportation Authority, No. 03-00194 (United States Bankruptcy Court, D. Puerto Rico July 14, 2014)

No reporter citation is stored for this case. This line is built from the stored case name, docket number, court and decision date.

The court’s opinion as stored in our database. This is the stored text for research. It is not legal advice; check the official source before you rely on it.