Montoya v. New Water St. Corp.
- Decided
- January 23, 2023
- Docket
- Index No. 702403/2020
- Status
- Unpublished
- Jurisdiction
- New York
Cited 0 timesNo negative treatment found in this library
What does the opinion say?
FILED: QUEENS COUNTY CLERK 01/26/2023 08:40 AM INDEX NO. 702403/2020 NYSCEF DOC. NO. 135 RECEIVED NYSCEF: 01/26/2023 Short Form Order NEW YORK SUPREME COURT - QUEENS COUNTY PRESENT: HON. ROBERT I. CALORAS PART 36 Justice ------------------------------------------------------------------X JORGE OSPINA MONTOYA, Index No. 702403/20 Plaintiff, Seq. No. 2 -against- NEW WATER STREET CORP., IMPARK WATER LLC and STRUCTURAL 1/26/2023 PRESERVATION SYSTEMS, LLC, Defendants. ------------------------------------------------------------------X The following papers numbered E68-E114, E118-28 read on this motion by the Plaintiff for an order granting him partial summary judgment on the issue of liability against Defendants New Water Street Corp (New Water) and Structural Preservations Systems, LLC (SPS) pursuant to New York State Labor Law 240(1) and pursuant to Labor Law 241(6); and the cross motion by Defendants New Water and SPS (Defendants) for an order granting said Defendants summary judgment dismissing the Complaint. PAPERS NUMBERED Notice of Motion-Affirmation-Exhibits-Memo of Law................. E68-E91 Stipulation, Letter………………………………………..………. E92, E126 Affirmation in Opposition-Memo of Law-Exhibits….………….. E93-E98 Reply Affirmation-Memo of Law……………………………….. E123-E125 Notice of Cross Motion-Affirmation-Exhibits-Memo of Law…… E99-E114 Affirmation in Opposition-Exhibits-Memo of Law.……............... E118-E122 Memo of Law in Reply Affirmation………....…........................... E127-E128 Upon the foregoing papers, it is ordered that Plaintiff’s motion is granted, and Defendants’ cross motion is granted in part and denied in part for the following reasons: According to the Complaint, Plaintiff was injured on December 27, 2019 while he was working on a scaffold-work platform at 55 Water Street, New York, New York due to Defendants’ violations of Labor Law 200, 240(1) and 241(6). It is undisputed that at the time of the accident, Defendant New Water was the property owner, Defendant SPS was the general contractor, and that Plaintiff was employed by C&D Iron Works, Inc. (“C&D”). In the first branch of Plaintiff’s motion, he moves for summary judgment against Defendants New Water and SPS on the issue of liability pursuant to Labor Law 240(1). Plaintiff argues that he is entitled to summary judgment against Defendants, because the dangerous and inadequate scaffold was the proximate cause of his accident. Plaintiff further argues that Defendants are precluded from claiming that he was a recalcitrant worker. In support thereof, Plaintiff submitted, among other things, the following: lease agreement between New Water and Defendant Impark; contract between New Water and SPS; Contract between SPS and C&D; photographs of the steel beam, scaffold, loose plywood blankets, his injuries, the grinder, and a sample hard hat with a face shield; Bills of Particulars; deposition transcript of nonparty John Leacock (Leacock), nonparty Chaitram Roopchan (Roopchan), Plaintiff, William Paolini (Paolini), and Patrick Kennedy (Kennedy). Plaintiff testified as follows: on December 27, 2017, he was employed as an iron worker for C&D at a parking lot renovation project at the subject premises. Roopchan, Plaintiff’s foreman, instructed Plaintiff to cut a steel beam on the ceiling, which was about ten to twelve feet above the ground with a grinder (an electric saw) located on the scaffold. He needed to use a scaffold to access the steel beam Roopchan directed him to cut. C&D already had scaffolds in place and assembled at 1 of 7 FILED: QUEENS COUNTY CLERK 01/26/2023 08:40 AM INDEX NO. 702403/2020 NYSCEF DOC. NO. 135 RECEIVED NYSCEF: 01/26/2023 the work location. Although there were three assembled scaffolds in place, the scaffold Plaintiff used was closest to the beam he needed to cut and was the only scaffold that had a grinder on the platform. He was shown several photographs, including a photograph marked as Defendants’ Exhibit 9, identifying the scaffold depicted therein as similar to the scaffold he had used and the area where the scaffold he used was located. Plaintiff stated that the three rungs on the scaffold in the photograph, were merely the sides of the scaffold and were not railings. After Roopchan instructed Plaintiff to cut the beam, Plaintiff inspected the scaffold, whereupon he saw that the scaffold did not have guard railings and “was shaking a lot”. He was only able to lock two of the four wheel locks on the scaffold, because two of the wheel locks on opposite sides were not working. After he locked two of the wheel locks, the scaffold kept shaking because the ground was not even because there were fire blankets and “plywoods” under the scaffold. He did not know who placed the fire blankets and “plywoods” under the scaffold. When he notified Roopchan that two of the wheel locks were not working, Roopchan told Plaintiff to fix the wheels and do his job. When Plaintiff told Roopchan the wheels could not be fixed, Roopchan told Plaintiff “to lock it as best as I could” otherwise “if you don’t want to do it, you can go home and rest”. Before he got on the scaffold, he also inspected the grinder that was on the platform of the scaffold. The grinder was yellow and manufactured by DEWALT. Upon inspecting the grinder he saw that it did not have a guard on it, but did have a blade on it. He had not removed the guard on the grinder and did not know who had removed it. He looked for another grinder from C&D, but could not find one. Roopchan told Plaintiff that C&D didn’t have more grinders available at that time. When Plaintiff told Roopchan that the grinder did not have a guard on it, Roopchan responded that Plaintiff “was complaining too much, that if I didn’t want to do my job, I had to go home”. After he inspected the scaffold and grinder, he used a ladder to get onto the platform of the scaffold, which was four feet above the ground. He was wearing his own protective equipment which included a hardhat, face shield, goggles, leather jacket and leather gloves. He was using the grinder for about a minute, when the scaffold moved and was shaking. The blade on the grinder got stuck in the steel beam located in the ceiling, whereupon the grinder kicked back towards him and hit him in his chest. After the grinder hit his chest, he let go of the grinder but the blade kept rotating and hit his face, causing his hardhat and face shield to fall off. When the grinder hit him, he lost his balance and fell. When he was falling he didn’t have anywhere to grab, because the scaffold did not have guard railings. After he fell, he was lying on his right side on the platform. His body parts below his waist remained on the platform, but the rest of his body was hanging from the platform. The scaffold did not break apart or tip over. Roopchan testified as follows: he was the foreman for C&D, and was Plaintiff’s supervisor at the time of the accident. He assembled the baker scaffold Plaintiff was using at the time of the accident. The scaffold was resting on or near loose plywood and blankets, and did not have guardrails. He instructed Plaintiff to cut down steel beams in the ceiling. He was outside of the work area when he heard Plaintiff scream. He was the first person to respond to the scene of the accident. Roopchan found Plaintiff with his feet on the platform, and his upper body slumped and hanging down over the side with the grinder tangled in Plaintiff’s shirt. Plaintiff’s body was tangled with the grinder at a lower height then the platform. Roopchan was able to untangle the grinder from the ground level, since Plaintiff was hanging down off the side. Roopchan wasn’t sure if Plaintiff’s face shield fell off while Plaintiff was falling or whether Plaintiff removed it after the accident due to the pain. Roopchan identified photos depicting loose plywood and blankets beneath the scaffolding. SPS had requested that C&D protect the floor. To protect the floor, C&D put blankets and plywood on the floor. When SPS inspected the site, SPS saw the blankets and wood covering the floor. The blankets could come loose by people moving around the work site and also by being pulled by the 2 of 7 FILED: QUEENS COUNTY CLERK 01/26/2023 08:40 AM INDEX NO. 702403/2020 NYSCEF DOC. NO. 135 RECEIVED NYSCEF: 01/26/2023 wheels of the scaffolding. The wood planks were not nailed down. The accident photographs depicted the scaffold Plaintiff used, which was partially on the cloth and partially on the plywood. He identified the grinder depicted in Defendants’ exhibit 3 as a green Mikita grinder. Prior to the accident, Plaintiff did not complain that the grinder was not working properly or lacked proper parts, nor did Plaintiff complain about any issues related to the scaffold. Leacock testified as follows: at the time of the accident he was working for C&D, performing welding about 15-20 feet away from Plaintiff. He was not facing Plaintiff when the accident occurred. He turned around when he heard Plaintiff scream, and observed Plaintiff entangled with the grinder. Plaintiff had his hard hat on but was not wearing his face shield. Leacock did not inspect the scaffold prior to the accident. After the accident, Leacock did not inspect the scaffold but it did look to be in working order. Leacock identified the photographs depicting the scaffold on top of the fire blankets. Paolini testified as follows: he is currently the Vice President of New Water, and was the project manager at the time of the accident. New Water relied on SPS to ensure the work site was safe and that the workers, including subcontractors, had proper safety equipment and were working safely, with proper procedures and equipment. He did occasionally walk through the job site to make sure it was tidy. Depending upon the work that was being performed, he had seen plywood, masonite and plastic covering the floor pursuant to the terms of the contract. He never saw any of the material placed on the floor “bunched up near the wheels of any of the baker’s scaffold”. His focus was proper operation of the garage, not worker safety. If during his walk through of the site he had seen anything that was “unsafe” and “not being used at that moment” he wouldn’t say anything, because he expected it wouldn’t be used in an unsafe manner. Kennedy testified as follows: at the time of the accident, he was employed as a foreman for SPS at the subject location. C&D provided and assembled its own scaffolding at the site, as well as their own safety equipment and tools. C&D was also responsible to protect the floor with blankets and wood, and to ensure that these materials were secure. He did not direct or instruct C&D what equipment to use on a daily basis. It was C&D’s responsibility to inspect their scaffolding, grinders, saws and personal fall protection to make sure they were in safe condition. It was also C&D’s responsibility to make sure the flooring was safe and secure before they put their scaffolding down. The photographs of the accident taken shortly after the accident showed that the wood was not lying flush over the blanket, which could cause the scaffold to become shaky. In opposition, Defendants argue that Plaintiff is not to entitled to summary judgment pursuant to Labor Law 240(1), because Plaintiff did not fall off the scaffold, nor did the scaffold brake, collapse or tip over. In addition, Plaintiff was not struck by a falling object that was being hoisted or secured as part of the work being performed. In the alternative, Defendants argue that issues of fact exist regarding how the accident occurred. The proponent of a summary judgment motion must tender evidentiary proof in admissible form eliminating any material issues of fact from the case (see Alvarez v Prospect Hosp., 68 NY2d 320 [1986]). Once this showing has been made, the burden shifts to the non-moving party to produce evidentiary proof in admissible form sufficient to establish the existence of material issues of fact that require a trial for resolution (see Alvarez v Prospect Hosp., supra; Zuckerman v City of New York, 49 NY2d 557 [1980]). Failure to make such a showing requires denial of the motion, regardless of the sufficiency of the opposing papers (see Winegrad v New York Univ. Med. Ctr., 64 NY2d 851, 853 [1985]). Labor Law § 240 (1) requires property owners and contractors to provide workers with "scaffolding, hoists, stays, ladders, slings, hangers, blocks, pulleys, braces, irons, ropes, and other 3 of 7 FILED: QUEENS COUNTY CLERK 01/26/2023 08:40 AM INDEX NO. 702403/2020 NYSCEF DOC. NO. 135 RECEIVED NYSCEF: 01/26/2023 devices which shall be so constructed, placed and operated as to give proper protection" to the workers. The purpose of the statute is to protect against "such specific gravity-related accidents as falling from a height or being struck by a falling object" (Ross v Curtis-Palmer Hydro-Elec. Co., 81 NY2d 494, 501 [1993]). "In determining the applicability of the statute, 'the single decisive question is whether [the] plaintiff's injuries were the direct consequence of [the] failure to provide adequate protection against a risk arising from a physically significant elevation differential' " (Lemus v New York B Realty Corp., 186 AD3d 1351, 1352 [2020], quoting Runner v New York Stock Exch., Inc., 13 NY3d 599, 603 [2009]). Here, the Court finds that Plaintiff established his prima facie burden of entitlement to summary judgment as a matter of law on the issue of liability on the Labor Law 240(1) cause of action through his submissions which established that Defendants’ failure to provide him with a safe scaffold to perform grinding work from an elevated position was a substantial cause of his accident. Plaintiff’s testimony establishes that the failure to provide a secure scaffold caused him to lose control of the grinder which caused his injuries. The need for a secure scaffold to do the work safely and properly was clear, and the manner in which Plaintiff injured himself was foreseeable. The Court also finds that Defendants failed to raise any triable issues of fact regarding the accident not having occurred due to a defective scaffold and grinder. Moreover, contrary to Defendants’ claims, the testimony and photographs Plaintiff submitted demonstrated that the subject scaffold did not have guard railings, and the railings Defendants referred to were merely the vertical members on which the scaffold planking rested upon. Moreover, even though Plaintiff’s entire body did not fall off the scaffold is of no consequence since harm directly flowed from the application of the force of gravity to his person (Lacey v Turner Constr. Co., 275 AD2d 734 , 735 [2d Dept. 2000] [“The fact that the plaintiff did not actually fall from the ladder is irrelevant as long as the harm directly flow[ed] from the application of the force of gravity to an object or person" [internal quotation omitted]; see also Johnsen v State, 207 AD3d 530 [2d Dept. 2022] [The fact that Plaintiff did not actually fall from the basket of a boom lift “is irrelevant as long as the harm directly flow[ed] from the application of the force of gravity to [her] person” [internal quotation omitted]; Abero v URS Greiner Woodward Clyde, 60 AD3d 878 [2d Dept. 2009] [As to Plaintiff’s Labor Law 240(1) claim, the fact that the Plaintiff did not fall completely off of the scaffolding is not controlling]). Additionally, it is also inconsequential that the scaffold did not break apart, collapse or tip over. Here, the scaffold rested upon an uneven wooden plank covering a blanket. Significantly, Plaintiff testified that if the scaffold had been equipped with guardrails, he would have had something to grab onto. Accordingly, the branch of Plaintiff’s motion seeking summary judgment against Defendants on his Labor Law 240(1) claim is granted. In the next branch of Plaintiff’s motion, he seeks summary judgment against Defendants on his Labor Law 241(6) claim, alleging that that Defendants violated 12 NYCRR 23-5.1(b), 23-1.5( c)(3), 23-5.1(f), and 23-5.18(b). Labor Law 241(6) “imposes a nondelegable duty of reasonable care upon owners and contractors to provide reasonable and adequate protection and safety ‘to persons employed in, or lawfully frequenting, all areas in which construction, excavation or demolition work is being performed’ ” (Rizzuto v L.A. Wenger Contr. Co., 91 NY2d 343, 348 [1998], quoting Labor Law § 241 [6]; Harrison v State of NY, 88 AD3d 951, 953 [2nd Dept 2011]; Romero v J & S Simcha, Inc., 39 AD3d 838 [2d Dept 2007]). In order to prevail under this section of the Labor Law, a Plaintiff must establish that specific safety rules and regulations of the Industrial Code promulgated by the Commissioner of the Department of Labor were violated (see Ross v Curtis-Palmer Hydro- Elec. Co., 81 NY2d 494 [1993]); Ares v State of New York, 80 NY2d 959 [1992]). The rule or 4 of 7 FILED: QUEENS COUNTY CLERK 01/26/2023 08:40 AM INDEX NO. 702403/2020 NYSCEF DOC. NO. 135 RECEIVED NYSCEF: 01/26/2023 regulation alleged to have been breached must be a specific, positive command and be applicable to the facts of the case (see Rizzuto v L.A. Wenger Contr. Co., 91 NY2d at 349 ). Initially, the Court finds that Defendants’ claim that Plaintiff is not entitled to summary judgment on his claim that Defendants violated 12 NYCRR 23-1.5( c)(3) and 5.18(b), because Plaintiff did not assert these violations in his Bill of Particulars nor has Plaintiff moved to amend his Bill of Particulars is without merit. It is well settled that “the failure to identify the specific [Industrial] Code provision allegedly violated in support of a Labor Law § 241 (6) cause of action either in the complaint or in the bill or supplemental bills of particulars is not necessarily fatal" (Kowalik v Lipschutz, 81 AD3d 782 [2d Dept. 2011]). “A plaintiff may make an allegation of an Industrial Code violation in support of a Labor Law § 241 (6) claim for the first time in opposition to a motion for summary judgment if the allegation involve[s] no new factual allegations, raise[s] no new theories of liability, and cause[s] no prejudice to the defendants" (id. [internal quotation omitted]). Here, the Court finds that Plaintiff’s claims alleging that Defendants’ violated 12 NYCRR 23-1.5( c)(3) and 5.18(b) do not raise new theories of liability, and that Defendants have failed to establish they were prejudiced by these claims. The Court also finds that Defendants have failed to set forth a sufficient basis to depart from the Second Department’s ruling in Perez v 286 Scholes St. Corp, 134 AD3d 1085 [2d Dept. 2015) that 12 NYCRR 23-1.5 is sufficiently specific to support a Labor Law 241(6) cause of action in light of Toussaint v Port Auth. of N.Y., 38 NY3d 89 (2022) is without merit. 12 NYCRR 23-5.1(b) provides that “The footing or anchorage for every scaffold erected on or supported by the ground, grade or equivalent surface shall be sound, rigid, capable of supporting the maximum load intended to be imposed thereon without settling or deformation and shall be secure against movement in any direction. Unstable supports, such as barrels, boxes, loose brick or loose stone, shall not be used”. Here, both Plaintiff and Roopchan testified that underneath the scaffold was wood planks covering a blanket. Plaintiff testified that the scaffold was shaking, and Roopchan testified that the wood plank was not secured to the ground. Accordingly, Plaintiff’s request for summary judgment on his claim that Defendants violated 12 NYCRR 23-1.5(b) is granted. 12 NYCRR 23-1.5( c)(3) provides, in pertinent part, that “All safety devices, safeguards and equipment in use shall be kept sound and operable, and shall be immediately repaired or restored or immediately removed from the job site if damaged”. Here, Plaintiff testified that when he notified Roopchan, the foreman, that the grinder did not have a guard, Roopchan directed him to use the grinder. Contrary to Defendants’ claims, the Court finds that section 23-1.5( c)(3) is sufficiently specific with respect to Plaintiff’s claims regarding the subject grinder (Becerra v Promenade Apts., Inc., 126 AD3d 557 [1st Dept. 2015] [“Since the final paragraph of section 23-1.5 (c) is functionally indistinguishable from the third sentence of section 23-9.2 (a), in that both mandate a distinct standard of conduct, we find that the Court of Appeals' reasoning in Misicki [ 12 NY3d 511 (2009)] applies here, and reject the dissent's suggestion that the preamble of section 23-1.5 precludes any reliance on the section for purposes of Labor Law § 241 (6)]”). Here, Plaintiff testified that when he notified Roopchan, C&D’s foreman, that the grinder did not have a guard, Roopchan directed that Plaintiff still use the grinder. Accordingly, Plaintiff’s request for summary judgment on his claim that Defendants violated 12 NYCRR 23-1.5( c)(3) is granted. 12 NYCRR 23-5.1(f) provides that “Every scaffold shall be maintained in good repair and every defect, unsafe condition or noncompliance with this Part (rule) shall be immediately corrected before further use of such scaffold”. Here, as set forth above both Plaintiff testified that the scaffold was uneven and shaky, and Roopchan conceded that the wooden plank below the scaffold was not 5 of 7 FILED: QUEENS COUNTY CLERK 01/26/2023 08:40 AM INDEX NO. 702403/2020 NYSCEF DOC. NO. 135 RECEIVED NYSCEF: 01/26/2023 secured to floor. Accordingly, Plaintiff’s request for summary judgment on his claim that Defendants violated 12 NYCRR 23-5.1(f) is granted 12 NYCRR 23-5.18(b) provides that “Safety railings required. The platform of every manually-propelled mobile scaffold shall be provided with a safety railing constructed and installed in compliance with this Part (rule)”. Here, Plaintiff testified that the scaffold did not have railings, and the photos of the scaffold Plaintiff submitted similarly showed that it did not have railing. In opposition, Defendants submitted an affidavit from Bernard P. Lorenz, P.E., a civil engineer and a copy of OSHA Fact Sheet for “Narrow Frame Scaffolds”. Mr. Lorenz opined that there is no regulatory requirement or construction industry standard in New York for Baker-type scaffolds to be equipped with safety railings on all open sides, when the platform height is seven feet or less. As such, Mr. Lorenz concluded that 12 NYCRR 23-5.18 (b) does not require a Baker-type scaffold with a platform height of seven feet to have a guardrail system. The Court finds that Defendants’ submission failed to raise a triable issue of fact regarding whether guardrails on the subject scaffold was required pursuant to 23-5.18(b). It is well settled that “code provisions specifically applicable to manually propelled scaffolds require safety railings without reference to the height of the scaffold”, i.e. 12 NYCRR 23-5.18 [b] (Vergara v SS 133 W. 21 , LLC, 21 AD3d 279 [1st Dept. 2005]). Here, Plaintiff’s testimony established that the lack of guardrails was the proximate cause of his accident. Accordingly, Plaintiff’s request for summary judgment on his claim that Defendants violated 12 NYCRR 23-5.18(b) is granted Turning to Defendants’ cross motion, the branch seeking summary judgment dismissing Plaintiff’s Labor Law 240(1) cause of action and the branch seeking to dismiss Plaintiff’s claims alleging Defendants violated 12 NYCRR 23-5.1(b), 23-1.5( c)(3), 23-5.1(f), and 23-5.18(b) are denied for the reasons set forth above. In opposition, Plaintiff opposes Defendants’ request to dismiss sections 23-5.1( c)(1),(d), ( e) and (j), 23-5.18(g) and 9.2. Therefore, the remaining code violations alleged in Plaintiff’s Bill of Particulars are dismissed. The Court finds that Defendants’ submissions established their prima facie entitlement to dismissal of Plaintiff’s claims that Defendants violated 12 NYCRR 23-5.1( c), (d) and (e). The Court also finds that Plaintiff failed to raise any triable issues of fact nor did he assert any claims establishing that these sections are applicable herein. The Court also finds that Defendants’ submissions failed to establish their prima facie entitlement to dismissal of Plaintiff’s claim that they violated 12 NYCRR 23-5.1(j). This section provides, in pertinent part, that the “open sides of all scaffold platforms . . . shall be provided with safety railings”, and those exempt from this provision include “[a]ny scaffold platform with an elevation of not more than seven feet . . . “. Here, the testimony established that the subject scaffold’s platform had an elevation of only four feet. Accordingly, Defendants’ request to dismiss Plaintiff’s claim alleging a violation of 12 NYCRR 23- 5.1(j) is denied. Next, the Court finds that Defendants’ submissions failed to establish their prima facie entitlement to dismissal of Plaintiff’s claim that they violated 12 NYCRR 23-5.18(g). This section provides that “[w]henever any such scaffold is in use and is occupied by any person, such scaffold shall rest upon a stable footing, the platform shall be level and the scaffold shall stand plumb. All caster or wheels shall be locked in position.” Here, the proof submitted herein established that the scaffold was not plumb to the floor nor were all the wheels locked. Accordingly, Defendants’ request to dismiss Plaintiff’s claim alleging a violation of 12 NYCRR 23-5.18(g) is denied. The Court also finds that Defendants established that the subject grinder was not “heavy machinery” and, as such, is not subject to 12 NYCRR 23-9.2 (Cabrera v Revere Condominium, 91 AD3d 695 [2d Dept. 2012], lv denied 19 NY3d 802 [2012]).
6 of 7 FILED: QUEENS COUNTY CLERK 01/26/2023 08:40 AM INDEX NO. 702403/2020 NYSCEF DOC. NO. 135 RECEIVED NYSCEF: 01/26/2023 In the next branch of the cross motion, Defendants move for summary judgment dismissing Plaintiff’s Labor Law 200 cause of action. Defendants argue that Plaintiff’s injuries arose from the manner in which the work was being performed, and that all of the scaffolds, grinders, and materials used to protect the floor were all provided by C&D, Plaintiff’s employer. Defendants further argue that the means and methods of the Plaintiff’s work were entirely directed by C&D, and that Defendants did not supervise, direct, or control any of the work Plaintiff was performing at the time of the accident. In opposition, Plaintiff argues that triable issues of fact exist regarding whether Defendants had constructive notice of the alleged dangerous condition that caused his injuries Labor Law 200 is a “codification of the common-law duty imposed upon an owner or general contractor to provide construction site workers with a safe place to work.” (Comes v New York State Elec. & Gas Corp., 82 NY2d 876, 877 [1993]). “Cases involving Labor Law § 200 fall into two broad categories: namely, those where workers are injured as a result of dangerous or defective premises conditions at a work site, and those involving the manner in which the work is performed.” (Ortega v Puccia, 57 AD3d 54, 61 [2d Dept 2008]). Where the manner and method of work are at issue in a Labor Law 200 analysis, the issue is whether the owner or contractor had the authority to supervise or control the work. (See Mitchell v Caton on the Park, LLC, 167 AD3d 865 [2d Dept 2018]; see also Poalacin v Mall Props., Inc., 155 AD3d 900 [2d Dept 2017]; Ortega v Puccia, supra).
Where a plaintiff’s injuries stem not from the manner in which the work was being performed, but, rather, from a dangerous condition on the premises, a property owner or contractor may be liable in common-law negligence and under Labor Law 200 only if the owner or contractor had control over the work site and either created the dangerous condition causing an injury, or failed to remedy the dangerous condition while having actual or constructive notice of it (See Abelleira v City of New York, 120 AD3d 1163 [2d Dept 2014]; see also Martinez v City of New York, 73 AD3d 993 [2d Dept 2010]; Van Salisbury v Elliott-Lewis, 55 AD3d 725 [2d Dept 2008]). Here, the Court finds that Defendants’ submissions failed to establish to their prima facie entitlement to summary judgment dismissing Plaintiff’s Labor Law 200 claim. Although Paolini, New Water’s project manager, testified that he during his walk throughs he never saw a scaffold resting on top of a blanket and wooden plank, Roopchan, C&D’s foreman, testified that when SPS inspected the site that SPS saw the blankets and wood covering the floor. Consequently, Defendants’ submissions failed to resolve all issues of fact regarding whether they had constructive knowledge of the alleged dangerous condition that caused Plaintiff’s accident. According, the branch of the cross motion seeking summary judgment dismissing Plaintiff’s Labor Law 200 claim is denied.
DATED: January 23, 2023 ___________________________ ROBERT I. CALORAS, J.S.C.
1/26/2023 7 of 7