Grimes v. VIRGINIA ELECTRIC & POWER COMPANY
- Decided
- February 27, 1957
- Docket
- 27
- Status
- Published
- Judges
- Higgins, Rodman
- Jurisdiction
- North Carolina
Cited 10 timesNo negative treatment found in this library
What later courts said
- holding that placement of additional lines and cross-arms on existing power poles by second power company imposed additional burden on easement entitling landowner to compensation — Farrell v. Vermont Electric Power Co., and Vermont Transco, LLC (2012)
Each line is a later court’s own words about this case, not a summary. Read the opinion before relying on it.
What does the opinion say?
HiggiNS, J.
The question presented is whether the plaintiff’s grant to Virginia Electric & Power Company authorized it in turn to grant to the City of Washington the right to attach electric lines and appurtenances, including a crossann, to the power company’s poles. The plaintiff contends he is entitled to collect compensation for the increased servitude thus placed on his land. On the other hand, the defendant contends the plaintiff’s grant was to the Virginia Electric & Power Company and to its successors and assigns, and permitted it to make the assignment to the City of Washington.
The answer to the defendant’s contention is that the Virginia Electric & Power Company has not assigned anything. It still retains its right to maintain its full complement of wires and other facilities and to transmit electricity within the full limits of its grant. The contract between the defendants permits the power company to retain all its facilities and, in addition, permits the City of Washington to transmit its own current by means of its own wires attached to the power company’s poles. The plaintiff was not a party to the contract between the defendants. The additional lines of the city, with the right to enter upon the lands for maintenance purposes, place an additional burden on plaintiff’s land without his consent. Two power companies enjoy an easement over his land. He granted only one. [*585] ' Any additional burden beyond the grant entitles the landowner to just compensation.
Light Co. v. Clark, 243 N.C. 577, 91 S.E. 2d 569;
Hildebrand v. Tel. Co., 219 N.C. 402, 14 S.E. 2d 252;
Crisp v. Light Co., 201 N.C. 46, 158 S.E. 845;
Rouse v. Kinston, 188 N.C. 1, 123 S.E. 482;
Teeter v. Telegraph Co., 172 N.C. 783, 90 S.E. 941;
Hodges v. Telegraph Co., 133 N.C. 225, 45 S.E. 572;
Phillips v. Telegraph Co., 130 N.C. 513, 41 S.E. 1022; Mordecai’s Law Lectures, 2d Ed., Vol. 1, pp. 467, 469, 470.
The plaintiff is entitled to go to the jury on the question of just compensation for the additional burden placed upon his land.
Reversed.
Rodman, J., took no part in the consideration or decision of this case.
Cite this
Grimes v. VIRGINIA ELECTRIC & POWER COMPANY, No. 27 (Supreme Court of North Carolina February 27, 1957)No reporter citation is stored for this case. This line is built from the stored case name, docket number, court and decision date.
The court’s opinion as stored in our database. This is the stored text for research. It is not legal advice; check the official source before you rely on it.