Case law · Highest court · Massachusetts

Security Safety Corp. v. Kuznicki

Decided
February 2, 1966
Status
Published
Judges
Wilkins, Cutter, Kirk, Reardon
Jurisdiction
Massachusetts

Cited 13 timesNo negative treatment found in this library

What later courts said

  • holding a 33 1/3% liquidated damage provision as unenforceable — Kelly v. Marx (1995)
  • liquidated damages providing for penalty of one-third of contract price unreasonable and unenforceable as a matter of law — Kelly v. Marx (1999)

Each line is a later court’s own words about this case, not a summary. Read the opinion before relying on it.

What does the opinion say?

Wilkins, C.J.

The defendants, Edmund and Rachel Kuznicki, signed a written contract with the plaintiff for the installation of a fire detection system on their premises in Blandford for the sum of $498. Their cancellation presents the question of the validity of a provision that “In the event of cancellation of this agreement . . . the owner agrees to pay 33%% of the contract price, as liquidated damages.” The trial judge held that the provision was unreasonable and void as a penalty. He found for the plaintiff in the amount of $1, and reported the correctness of his finding to the Appellate Division, which dismissed the report. The plaintiff appealed.

The case was submitted on agreed facts. The contract was signed the evening of March 25,1964. The defendants [*158] made a deposit of $1 and agreed to pay the balance in “cash Sept. 15th.” About nine o’clock on the morning following the signing of the contract the defendants can-celled “before the plaintiff did anything in respect to the work it was to perform.” [1]

“No evidence was agreed upon or offered as to the actual damage suffered by the plaintiff.” There was no error. The case is governed in all respects by A-Z Servicenter, Inc. v. Segall, 334 Mass. 672. For aught that appears, the damages in event of breach were not going to be difficult of ascertainment. See Restatement: Contracts, § 339; Williston, Contracts (3d ed.) § 776; Corbin, Contracts, § 1060, p. 350; 25 C. J. S., Damages, § 107, pp. 1048-1050. Time was lacking for an opportunity for the plaintiff to incur much expense of performance. The stipulated sum is unreasonably and grossly disproportionate to the real damages from the breach. In these circumstances, the aggrieved party will be awarded no more than his actual damage.

Makletzova v. Diaghileff, 227 Mass. 100, 108.

A-Z Servicenter, Inc. v. Segall, supra, 675. McCormick, Damages, § 148, p. 605. Macneil, Power of Contract and Agreed Remedies, 47 Cornell L. Q. 495, 502-503, 505. Compare the rule for the sale of goods in the Uniform Commercial Code. Gr. L. c. 106, § 2-718 (l). [2]

Of actual damage there was no evidence.

Order dismissing report affirmed. [1]

The plaintiff denies that it agreed to this fact. The record, however, sheds no light on this contention. [2]

The record does not disclose whether this section applies.

Cite this

Security Safety Corp. v. Kuznicki (Massachusetts Supreme Judicial Court February 2, 1966)

No reporter citation is stored for this case. This line is built from the stored case name, docket number, court and decision date.

The court’s opinion as stored in our database. This is the stored text for research. It is not legal advice; check the official source before you rely on it.