PER CURIAM.

Albin Stevedore Company appeals from a summary judgment dismissing its first cause of action in a suit which it brought against Central Rigging and Contracting Corporation. The question presented is whether the subject matter of that cause of action had been submitted to arbitration along with the subject matter of appellant’s second cause of action, and had therefore been disposed of by the award of the arbitrations.

We hold that under the undisputed facts established in connection with cross-motions for summary judgment, the subject matter of the first cause of action was a part of the claim submitted to the arbitrators. Their award in “full settlement of all claims submitted” therefore disposed of that cause of action, leaving nothing pending in the district court.

The judgment is affirmed.

Cite this

Albin Stevedore Company, a Washington Corporation v. Central Rigging & Contracting Corporation, No. 17609_1 (Court of Appeals for the Ninth Circuit August 16, 1962)

No reporter citation is stored for this case. This line is built from the stored case name, docket number, court and decision date.

The court’s opinion as stored in our database. This is the stored text for research. It is not legal advice; check the official source before you rely on it.