Mississippi Valley Gas Company v. Federal Power Commission
- Decided
- February 7, 1973
- Docket
- 72-1157
- Status
- Published
- Judges
- Brown, Bell, Morgan
- Jurisdiction
- Federal
Cited 0 timesNo negative treatment found in this library
What does the opinion say?
PER CURIAM:
This case is one of a group arising from the adoption by the Federal Power Commission of “curtailment plans” filed by United Gas Pipe Line Company. These curtailment plans were the outgrowth of an order promulgated by the FPC and were aimed at serving the public interest by establishing a rational scheme of allocation of available natural gas in light of the current, somewhat critical, shortage of this much-used fuel. Due to this shortage, pipeline companies found that they would not be able to meet all of their current contractual obligations for delivery of gas. At present, the FPC has not finally approved any of the curtailment plans in question. It has, however, issued two orders, Opinions 606 and 606A, which are reviewable and are now challenged by numerous parties on several grounds before this court. Each of the contentions raised by these petitioners will be considered separately below.
FPC Jurisdiction to Enter Curtailment Orders Affecting Sales for Resale At the time this action was initially filed with this court, we had previously held in Louisiana Power & Light Company v. United Gas Pipe Line Company, 5 Cir. 1972, 456 F.2d 326, that the Commission did not have authority under the Natural Gas Act to order curtailment of sales to direct sale customers. In Federal Power Commission v. Louisiana Power & Light Company, 1972, 406 U.S. 621, 92 S.Ct. 1827, 32 L.Ed.2d 369, the United States Supreme Court reversed that determination by this circuit and held that the Commission was authorized to entertain curtailment plans with regard to both direct sales and sales for resale. Therefore, this opinion by the Supreme Court has conclusively settled this first issue raised by these petitioners and the Commission’s jurisdiction is no longer subject to challenge on this basis.
Objection to Lack of a “Threshold Determination” by FPC as to Need for Curtailment In a supplementary brief filed after oral argument, these petitioners strongly object to the imposition by the FPC of curtailment plans filed by the pipelines without some preliminary hearing or determination that curtailment was warranted. We feel that we have adequately addressed these assertions in Alabama Gas Corporation v. Federal Power Commission, 5 Cir. 1973, 476 F.2d 142.
Therefore the opinions and orders of the FPC as to the issues raised by these petitioners are affirmed.
Cite this
Mississippi Valley Gas Company v. Federal Power Commission, No. 72-1157 (Court of Appeals for the Fifth Circuit February 7, 1973)No reporter citation is stored for this case. This line is built from the stored case name, docket number, court and decision date.
The court’s opinion as stored in our database. This is the stored text for research. It is not legal advice; check the official source before you rely on it.