Case law · Appeals court · Federal

Swanson-Dean Corporation v. Seattle District Council of Carpenters, Seattle District Council of Carpenters v. Swanson-Dean Corporation

Decided
May 26, 1981
Docket
77-3891, 77-3892
Status
Published
Judges
Skelton, Goodwin, Ferguson
Jurisdiction
Federal

Cited 2 timesNo negative treatment found in this library

What later courts said

  • "The (subcontracting) language accepted by the employer is analogous to that used in guarantor agreements, or agreements of indemnification, and it is our conclusion that the parties intended that the employer would pay if the subcontractor did not" — Brogan v. Swanson Painting Co (1982)
  • “The [subcontracting] language accepted by the employer is analogous to that used in guarantor agreements, or agreements of indemnification, and it is our conclusion that the parties intended that the employer would pay if the subcontractor did not” — Brogan v. Swanson Painting Co. (1982)

Each line is a later court’s own words about this case, not a summary. Read the opinion before relying on it.

What does the opinion say?

GOODWIN, Circuit Judge.

Swanson-Dean, a construction contractor, appeals from two orders which had the result of validating a challenged subcontracting clause in a collective bargaining agreement. We affirm.

In 77-3891, the district court granted the carpenter union’s motion for summary judgment. This order dismissed Swanson-Dean’s action to enjoin arbitration.

In 77-3892, the district court also granted the carpenter union’s motion for summary judgment in the union’s action for enforcement of the arbitrator’s award. The award required Swanson-Dean to pay trust fund contributions for work subcontracted in violation of the subcontracting clause and enjoined Swanson-Dean from future violations of the subcontracting clause.

On April 9, 1980, we heard argument in this case but deferred submission pending an expected en banc decision in a number of consolidated appeals. Those cases were decided by this court en banc on April 17, 1981. The decision disposes of the major issues in the present case.

Pacific Northwest Chapter, etc., et al. v. N.L.R.B., Nos. 78-3468, 78-3469, 78-3487, 78-3619, 79-7011 (9th Cir. April 17, 1981).

Because we have now held that collective bargaining agreements in the construction industry may lawfully contain clauses which limit employers in their choice of subcontractors to those having agreements with the appropriate unions, there was no substantial defect in the challenged agreement in this case.

It also follows that because the agreement was valid the employer had no defense to the arbitration clause. The case was properly submitted to arbitration and the arbitration award is entitled to enforcement.

Affirmed.

SKELTON, Senior Judge.

I respectfully dissent for all of the reasons stated by Judges Sneed, Choy, Anderson and Farris in their dissenting opinions in Pacific Northwest Chapter, etc., et al. v. N.LR.B., Nos. 78-3468, 78-3469, 78-3487, 78-3619, and 79-7011 (9th Cir. April 17, 1981), which I adopt by reference. In addition, it is my opinion that the agreement was invalid and consequently the arbitration award should not be enforced. I would reverse the decision of the district court.

Cite this

Swanson-Dean Corporation v. Seattle District Council of Carpenters, Seattle District Council of Carpenters v. Swanson-Dean Corporation, No. 77-3891, 77-3892 (Court of Appeals for the Ninth Circuit May 26, 1981)

No reporter citation is stored for this case. This line is built from the stored case name, docket number, court and decision date.

The court’s opinion as stored in our database. This is the stored text for research. It is not legal advice; check the official source before you rely on it.