Munilla Construction Management, LLC
- Decided
- October 6, 2016
- Docket
- ASBCA No. 60664
- Status
- Published
- Judges
- Stempler
- Jurisdiction
- Federal
Cited 0 timesNo negative treatment found in this library
What does the opinion say?
ARMED SERVICES BOARD OF CONTRACT APPEALS Appeal of -- ) ) Munilla Construction Management, LLC ) ASBCA No. 60664 ) Under Contract No. W912EP-13-C-0008 ) APPEARANCE FOR THE APPELLANT: Karl Dix, Jr., Esq. Smith, Currie & Hancock LLP Atlanta, GA APPEARANCES FOR THE GOVERNMENT: Thomas H. Gourlay, Jr., Esq. Engineer Chief Trial Attorney Joshua R. Holmes, Esq. B. Seth Johnson, Esq. Engineer Trial Attorneys U.S. Army Engineer District, Jacksonville ORDER OF DISMISSAL The dispute has been settled. The appeal is dismissed with prejudice.
Dated: 6 October 2016 Administrative Judge Acting Chairman Armed Services Board of Contract Appeals I certify that the foregoing is a true copy of the Order of Dismissal of the Armed Services Board of Contract Appeals in ASBCA No. 60664 , Appeal ofMunilla Construction Management, LLC, rendered in conformance with the Board's Charter.
Dated:
JEFFREY D. GARDIN Recorder, Armed Services Board of Contract Appeals
Cite this
Munilla Construction Management, LLC, No. ASBCA No. 60664 (Armed Services Board of Contract Appeals October 6, 2016)No reporter citation is stored for this case. This line is built from the stored case name, docket number, court and decision date.
The court’s opinion as stored in our database. This is the stored text for research. It is not legal advice; check the official source before you rely on it.