Wilgram v. Town of Sedgwick
- Decided
- June 26, 1991
- Status
- Published
- Judges
- Brody, Collins, Glassman, McKusick, Roberts, Wathen
- Jurisdiction
- Maine
Cited 7 timesNo negative treatment found in this library
What later courts said
- determining that the good cause exception could not save an abutter’s untimely appeal that was filed seven months after the issuance of the building permit and seventy-six days after the 16 abutter obtained actual notice of the project — Richard Tominsky v. Town of Ogunquit et al. (2023)
- "None of the special circumstances that might justify granting her an exception to the filing rule is to be found here." — Gallagher v. Town of Chebeague Island (2023)
- appeal seven months after issuance of permit not timely when plaintiff delayed taking action for seventy-six days from notice of construction and showed no significant impairment to use and enjoyment of property — Boisvert v. King (1992)
Each line is a later court’s own words about this case, not a summary. Read the opinion before relying on it.
What does the opinion say?
McKUSICK, Chief Justice.
In this action brought pursuant to M.R. Civ.P. 80B, plaintiff Isabell Y. Wilgram appeals the affirmance in Superior Court (Hancock County, Smith, J.) of the decision of the Town of Sedgwick’s Board of Appeals, denying plaintiff’s appeal of a building permit issued by the Town’s Planning Board to defendant Robert Duffy. Because plaintiff’s appeal to the Board of Appeals was untimely, we vacate the Superior Court judgment and remand for dismissal of this action.
Plaintiff is the sole trustee of the Quan-soo Trust, which owns waterfront property on Walker Pond in Sedgwick. Abutting that property is land owned by defendant Robert Duffy. On February 14, 1989, the Planning Board issued a permit to Duffy to build a camp on his property. On or before July 4, 1989, plaintiff knew that construction of the camp was underway on the Duffy property. She did not file her appeal with the Board of Appeals, challenging the issuance of Duffy’s permit, until September 18, 1989. Following a hearing, the Board of Appeals denied plaintiff’s appeal, both on the ground that the Planning Board had acted properly in issuing a permit to Duffy for the construction of his camp and on the ground that plaintiff’s appeal was untimely, having been filed more than 60 days after the Planning Board had issued Duffy’s permit. Plaintiff then commenced the present action seeking review of the Board of Appeals decision. The court held “that the findings of the Board of Appeals are supported by the record” and that plaintiff “had not shown the actions of the Planning Board ... to be clearly contrary to provisions of Sedg-wick’s Shoreland Zoning Ordinance.” The court also ruled that plaintiff’s appeal to the Board of Appeals was not timely and could have been dismissed on that ground.
The provision in the Town’s Shore-land Zoning Ordinance that allows for an appeal from the Planning Board to the Board of Appeals prescribes no time limit for the filing of the appeal. See Sedgwick, Me., Shoreland Zoning Ordinance, § 13(C)(2) (May 29, 1974). Nor does the applicable statute set a deadline for filing an appeal from a building permit. See 30-A M.R.S.A. § 4103(5) (Pamph.1990). Nearly two decades ago we ruled that when both the zoning ordinance and the statute are silent on the length of the allowable appeal period, a “reasonable” period is implied, and normally that reasonable period will be 60 days running from the appealed-from action or failure to act. See Keating v. Zoning Board of Appeals of Saco, 325 A.2d 521, 524-25 (Me.1974). We recognize that “infrequent and narrow exceptions” to the 60-day rule should be permitted in those “special circumstances which would result in a flagrant miscarriage of justice unless, within a narrowly extended range, a time longer than the general norm is held ‘reasonable.’ ” Id. at 524. The Keating rule was designed to “achieve a highly desirable certainty and simultaneously permit the flexibility necessary ... to avoid the utter arbitrariness which, on occasion, can be shocking to conscience.” Id.
In the case at bar, plaintiff did not file her appeal with the Board of Appeals until a full seven months after the Planning Board had issued Duffy the permit for building his camp, long after the 60-day deadline. None of the special circumstances that might justify granting her an exception to the filing rule is to be found here. Cf. Gagne v. Cianbro Corp., 431 A.2d 1313 (Me.1981) (special circumstances found on specific facts to justify exception to 60-day rule). Even after learning about Duffy’s construction, plaintiff waited at least another 76 days before filing an appeal with the Board of Appeals. Further, she has shown no significant impairment to the use and enjoyment of the Trust’s property as a result of Duffy’s construction of a camp on his adjoining lot.
We agree with the Superior Court’s finding that plaintiff’s appeal to the Board of Appeals was untimely, but disagree with the court’s reaching the merits of the case. [*489] The untimeliness of plaintiffs filing, an issue that was squarely raised before the Board of Appeals, left it with no legal authority to hear and decide the appeal from the Planning Board. See Keating v. Zoning Board of Appeals of Saco, 325 A.2d at 525. The court had no effective administrative decision to review and consequently should have dismissed plaintiffs action.
The entry is:
Judgment vacated; case remanded to Superior Court for dismissal of this action.
All concurring.
Cite this
Wilgram v. Town of Sedgwick (Supreme Judicial Court of Maine June 26, 1991)No reporter citation is stored for this case. This line is built from the stored case name, docket number, court and decision date.
The court’s opinion as stored in our database. This is the stored text for research. It is not legal advice; check the official source before you rely on it.