Case law · Appeals court · New York

Buffalo Builders Supply Co. v. Reeb

Decided
June 29, 1926
Status
Published
Jurisdiction
New York

Cited 0 timesNo negative treatment found in this library

What does the opinion say?

Per Curiam.

The transaction which is the subject of this suit involved the sale by defendant to plaintiff of a “ builders’ supply business,” including a stock of goods, equipment and good will. This sale was made in December, 1913. In February, 1914, plaintiff brought this action for rescission because of what has been found to be “ a wilful violation of material part of the contract ” by defendant. (199 App. Div. 951:) The interlocutory judgment, modified and affirmed in this court, granted rescission and provided for an equitable restoration of the parties to the status quo through an accounting.

There was great delay in bringing the action to trial and reaching an interlocutory judgment. There was further delay in having the accounting. Both parties seem to be responsible for this result. In the meantime the plaintiff had sold the goods, used up the equipment and eventually had gone out of business, and its books and records had largely been destroyed. Actual restoration was impossible. In obedience to the terms of orders [*191] made years before, the learned referee has made a conscientious and painstaking effort to adjust the accounts between the parties by taking the best evidence available on the matters in dispute. It would have been sufficient under the conditions then existing if defendant had been allowed the inventory price of the goods, representing the fair value agreed upon at the time of sale. This would have been equitable under the circumstances; but he has received more than that by being allowed profits on sales made by plaintiff.

The defendant, not the plaintiff, was the wrongdoer; and there was no conversion by the latter of the goods purchased under the contract, afterward rescinded for subsequent willful violative acts by the defendant. We think, considering the period of more than twelve years that has elapsed between the making of the contract and the accounting, that the referee has reached a practical solution of a difficult problem, and that the judgment founded thereon should not be disturbed.

The judgment and order should be affirmed, with costs.

Present — Htjbbs, P. J., Clark, Davis, Crouch and Taylor, JJ. All concur.

Judgment and order affirmed, with costs.

Cite this

Buffalo Builders Supply Co. v. Reeb (Appellate Division of the Supreme Court of the State of New York June 29, 1926)

No reporter citation is stored for this case. This line is built from the stored case name, docket number, court and decision date.

The court’s opinion as stored in our database. This is the stored text for research. It is not legal advice; check the official source before you rely on it.