Martin, J.

The plaintiff seeks to recover the amount he alleges to be due on a contract entered into by the parties to this action on the 21st day of July, 1923, for installing the plumbing, gasfitting and hot water systems, as well as a satisfactory steam heating plant in a two-family house being constructed by the defendants.

The complaint alleges full performance. There is no allegation of waiver; and recovery is not sought on the theory of substantial performance. The answer is a denial.

The findings of fact and conclusions of law signed by the trial justice, are to the effect that the contract was fully performed in all respects and that the plaintiff is entitled to recover the contract price.

[*673] ' To perform this contract it would have been necessary to install at least twelve radiators. The plaintiff testified that but four radiators were installed by him, although he knew several more were required to properly heat the premises.

It was not only established by the evidence of defendants’ witnesses, but admitted by the plaintiff that the contract was not fully performed.

The judgment should be reversed, with costs, and the complaint dismissed, with costs.

Dowling, P. J., Finch, McAvoy and O’Malley, JJ., concur.

Judgment reversed, with costs, and complaint dismissed, with costs. Settle order on notice.

Cite this

Goros v. Pirk (Appellate Division of the Supreme Court of the State of New York June 3, 1927)

No reporter citation is stored for this case. This line is built from the stored case name, docket number, court and decision date.

The court’s opinion as stored in our database. This is the stored text for research. It is not legal advice; check the official source before you rely on it.