Central Foundry Co. v. Dower
- Decided
- November 15, 1933
- Status
- Published
- Jurisdiction
- New York
Cited 0 timesNo negative treatment found in this library
What does the opinion say?
Judgment determining that [*927] the lien of the Central Foundry Company is invalid as against the village of Ballston Spa reversed, on the law and facts, with costs, and judgment granted in favor of the Central Foundry Company against the village, under its lien, for the sum of $4,481.30, with interest from September 1, 1929. Findings of fact numbered 2, 3, 4, 5, 7 and 8 are reversed, and the court makes a new finding that the time of completion of the contract between the village and the general contractor was to be determined by the final certificate of the engineer, and that the work to be performed under the contract was not substantially completed until after the date of the filing of the claimant’s lien. Hill, P. J., McNamee and Heffernan, JJ., concur; Crapser and Bliss, JJ., dissent.
Cite this
Central Foundry Co. v. Dower (Appellate Division of the Supreme Court of the State of New York November 15, 1933)No reporter citation is stored for this case. This line is built from the stored case name, docket number, court and decision date.
The court’s opinion as stored in our database. This is the stored text for research. It is not legal advice; check the official source before you rely on it.