Case law · Trial court · New York

Miles v. Dover Furnace Iron Co.

Decided
July 2, 1889
Status
Published
Judges
Dykhan
Jurisdiction
New York

Cited 0 timesNo negative treatment found in this library

What does the opinion say?

Dykhan, J.

This action was commenced by the plaintiff for the twofold purpose of establishing a lease to him of the right to mine and take ore from the ore-beds of the Dover Furnace Company for 12 years, and also to recover from the Dover Furnace Company the damages sustained by him by reason of the failure o? that company to deliver him iron ore from its mines, in accordance with a contract between the parties for the delivery of such ore. The cause was tried before a judge without a jury, and the plaintiff recovered a, judgment for his damages, but failed to obtain a judgment for the specific performance of the agreement to execute the lease. The defendant appealed from that portion of the judgment entered against it, and the plaintiff appealed from the portion of the judgment which denied him specific relief. The action involves only facts, and the trial judge has made findings which are extremely full, and, after a most careful examination, we find them entirely satisfactory. Neither do we find any error in the record. The judgment is therefore affirmed on the opinion of the trial judge, without costs to either party.

Cite this

Miles v. Dover Furnace Iron Co. (New York Supreme Court July 2, 1889)

No reporter citation is stored for this case. This line is built from the stored case name, docket number, court and decision date.

The court’s opinion as stored in our database. This is the stored text for research. It is not legal advice; check the official source before you rely on it.