Case law · Appeals court · New York

Pinnacle Construction, Inc. v. City of Syracuse

Decided
December 22, 2006
Status
Published
Jurisdiction
New York

Cited 0 timesNo negative treatment found in this library

What does the opinion say?

Appeals from an order of the Supreme Court, Onondaga County (Edward D. Garni, J.), entered November 30, 2005 in a breach of contract action. The order, among other things, denied the motion of third-party defendant for summary judgment dismissing the amended third-party complaint and plaintiffs motion for summary judgment.

It is hereby ordered that the order so appealed from be and the same hereby is unanimously affirmed without costs.

Memorandum: Plaintiff commenced this action to recover sums allegedly due for additional work performed in the removal and reinstallation of a booster pump station in defendant, City of Syracuse (City). The City then commenced a third-party action seeking, inter alia, contractual indemnification from third-party defendant, the engineering firm that provided consulting services on the project. Supreme Court properly denied third-party defendant’s motion seeking summary judgment dismissing the amended third-party complaint and plaintiff’s cross motion seeking summary judgment on the amended complaint. Both third-party defendant and plaintiff failed to meet their respective initial burdens of establishing their entitlement to judgment as a matter of law (see generally CPLR 3212 [b]; Alvarez v Prospect Hosp., 68 NY2d 320, 324 [1986]). Present—Scudder, PJ., Martoche, Centra and Green, JJ.

Cite this

Pinnacle Construction, Inc. v. City of Syracuse (Appellate Division of the Supreme Court of the State of New York December 22, 2006)

No reporter citation is stored for this case. This line is built from the stored case name, docket number, court and decision date.

The court’s opinion as stored in our database. This is the stored text for research. It is not legal advice; check the official source before you rely on it.