Ruckle & Guarino, Inc. v. Hangan

Decided
March 4, 2008
Status
Published
Jurisdiction
New York

Cited 5 timesNo negative treatment found in this library

What does the opinion say?

To establish the right to enforce a mechanic’s lien, the contractor, or in this case the subcontractor, must make a prima facie case that the lien is valid, and that it is entitled to the amount asserted in the lien (8 Warren's Weed, New York Real Property § 92.11 [3] [a] [5th ed], citing Cramer v Esswein, 220 App Div 10 [1927]; see LHV Precast v Woodstock Lawn & Home Maintenance, 296 AD2d 736 [2002]). Plaintiff did not adduce sufficient evidence to establish prima facie entitlement to summary judgment enforcing the lien. Notably, the proposal on [*268] which plaintiff relies postdates the work performed, and plaintiffs evidence failed to establish that plaintiff is entitled to the amount asserted in the lien, i.e., $80,000. Concur—Andrias, J.P., Friedman, Buckley, McGuire and Moskowitz, JJ.

Cite this

Ruckle & Guarino, Inc. v. Hangan (Appellate Division of the Supreme Court of the State of New York March 4, 2008)

No reporter citation is stored for this case. This line is built from the stored case name, docket number, court and decision date.

The court’s opinion as stored in our database. This is the stored text for research. It is not legal advice; check the official source before you rely on it.