In re the Arbitration between Maizuru Shipbuilding & Engineering Co.
- Decided
- June 30, 1966
- Status
- Published
- Jurisdiction
- New York
Cited 3 timesNo negative treatment found in this library
What does the opinion say?
Order, entered April 25, 1966, unanimously reversed and vacated, on the law and the facts, with $30 costs and disbursements to petitioner-appellant; motion by respondent for the appointment by the court of an arbitrator in behalf of petitioner, denied; and the appointment by the petitioner of [*542] Herbert Lee Seward as its arbitrator, confirmed. The designation by the petitioner of an arbitrator as required by the contract between the parties was delayed pending a proceeding instituted by the' petitioner for a stay of arbitration and pending the determination of .an appeal from an order denying the stay, and it does not appear that the petitioner’s default, if any, in naming its arbitrator, was deliberately or willfully suffered. The right to appoint an arbitrator is a substantial right (Matter of Lipschutz [Gutwirth], 304 N. Y. 58, 65); and, under the circumstances here, we conclude that it was improper to unconditionally deprive petitioner of this right. ( See Matter of Ferris [Perkins], 257 App. Div. 949; Matter of Utility Oil Corp., 10 F. Supp, 678.) Concur — Stevens, J, P., Eager, Steuer and Capozzoli, JJ.
Cite this
In re the Arbitration between Maizuru Shipbuilding & Engineering Co. (Appellate Division of the Supreme Court of the State of New York June 30, 1966)No reporter citation is stored for this case. This line is built from the stored case name, docket number, court and decision date.
The court’s opinion as stored in our database. This is the stored text for research. It is not legal advice; check the official source before you rely on it.