Case law · Appeals court · New York

Braun Equipment Co. v. Meli Borelli Associates

Decided
October 19, 1995
Status
Published
Jurisdiction
New York

Cited onceNo negative treatment found in this library

What does the opinion say?

—Order, Supreme Court, New York County (Alice Schlesinger, J.), entered February 3, 1995, which granted defendant and interpleading plaintiff Credit Suisse’s motion to stay arbitration demanded by interpleaded defendant Greene Mechanical Corp., unanimously affirmed, without costs.

The prime contract at bar (the "Construction Management Agreement”) expressly precludes third-party privity. The subcontract (the "Plumbing Contract”) has language incorporating the prime contract’s terms by reference. Accordingly, the subcontractor is not in privity with the tenant (who acts as an owner for present purposes), and the subcontractor’s recourse is against the prime contractor only (see, Alvord & Swift v Muller Constr. Co., 46 NY2d 276, 280). Concur—Sullivan, J. P., Kupferman, Williams and Tom, JJ.

Cite this

Braun Equipment Co. v. Meli Borelli Associates (Appellate Division of the Supreme Court of the State of New York October 19, 1995)

No reporter citation is stored for this case. This line is built from the stored case name, docket number, court and decision date.

The court’s opinion as stored in our database. This is the stored text for research. It is not legal advice; check the official source before you rely on it.