Case law · Highest court · Pennsylvania

Blair v. Peck

Decided
July 1, 1881
Status
Published
Jurisdiction
Pennsylvania

Cited onceNo negative treatment found in this library

What does the opinion say?

Per Curiam :

The lease in this case contained these provisions : “ The party of the second part covenants to drill and have a well ready for pumping within six months from this date, and commence operations within thirty days from the date of this instrument. If said second party shall cease operations at any time for the term of three mouths, it shall work a forfeiture.” A previous covenant provided that “ if successful ” he should “prosecute the business without interruption for the common benefit of all the parties.” It is not denied that the well had been drilled, and that it was in operation without ceasing, but it was contended that the defendant was bound to drill and operate other wells so as to prevent the oil from being exhausted by wells on contiguous property. This might have been provided for by conditions similar to the one recited, but in their absence the learned judge was entirely right in holding that there was no forfeiture. The remedy on the covenant to prosecute the business for the common benefit was not by ejectment, but an action of covenant.

Judgment affirmed.

Cite this

Blair v. Peck (Supreme Court of Pennsylvania July 1, 1881)

No reporter citation is stored for this case. This line is built from the stored case name, docket number, court and decision date.

The court’s opinion as stored in our database. This is the stored text for research. It is not legal advice; check the official source before you rely on it.