Case law · Highest court · Massachusetts

Davis v. Galloupe

Decided
November 15, 1872
Status
Published
Judges
Chapman
Jurisdiction
Massachusetts

Cited 6 timesNo negative treatment found in this library

What does the opinion say?

Chapman, C. J.

By the express terms of the contract set forth, the plaintiffs were to furnish the granite mentioned according to the plans and specifications furnished by the architect named, as fast as he might require, and all the fitting and rebating necessary, and were to do it for the sum named. The defendant was to pay the price specified, on the terms and conditions expressed, but did not agree to furnish any patterns. It appears that it was necessary to have such patterns; but this was necessary as an incident to the performance of their work by the plaintiffs according to their contract, in the same sense that it was necessary to have tools and'workmen. As the plaintiffs actually prepared the patterns, it is obvious °that it was not necessary that the defendant should furnish them to enable the plaintiffs to do the work. By the legal construction of such a contract, the plaintiffs were to furnish the patterns. A usage that the defendant should pay for them would be contrary to the terms or construction of the contract, and therefore would not not be valid. Potter v. Smith, 103 Mass. 68. Exceptions sustained.

Cite this

Davis v. Galloupe (Massachusetts Supreme Judicial Court November 15, 1872)

No reporter citation is stored for this case. This line is built from the stored case name, docket number, court and decision date.

The court’s opinion as stored in our database. This is the stored text for research. It is not legal advice; check the official source before you rely on it.