State ex rel. Utilities Commission v. Edmisten
- Decided
- August 19, 1986
- Docket
- No. 549A84
- Status
- Published
- Judges
- Billings
- Jurisdiction
- North Carolina
Cited 0 timesNo negative treatment found in this library
What does the opinion say?
ORDER UPON receipt and consideration of the order of the Supreme Court of the United States in this cause, issued 23 June 1986, the following order was entered and is hereby certified to the North Carolina Utilities Commission:
[*280] “This case is remanded to the North Carolina Utilities Commission for further proceedings consistent with this Court’s opinion filed herein on 13 August 1985 but not inconsistent with the opinion of the United States Supreme Court in Nantahala Power and Light Company, et al. v. Thornburg, et al., No. 85-568, decided 17 June 1986, 476 U.S. —, 90 L.Ed. 2d 943 (1986).
By order of the Court in conference, this the 19th day of August 1986. s/Billings, J.
For the Court”
Cite this
State ex rel. Utilities Commission v. Edmisten, No. 549A84 (Supreme Court of North Carolina August 19, 1986)No reporter citation is stored for this case. This line is built from the stored case name, docket number, court and decision date.
The court’s opinion as stored in our database. This is the stored text for research. It is not legal advice; check the official source before you rely on it.