Case law · Appeals court · Ohio

Ferro Machine & Foundry Co. v. Willson Ave. Lumber Co.

Decided
December 18, 1922
Docket
No. 4090
Status
Published
Judges
Sullivan
Jurisdiction
Ohio

Cited 0 timesNo negative treatment found in this library

What does the opinion say?

SULLIVAN, J.' . Epitomized Opinion A contractor constructed a garage for the machine company and the lumber company furnished the material for the construction. The lumber was furnished at different times and the last lot of lumber was used for building forms for a driveway from the garage to the street. In an attempt by the lumber company to foreclose a mechanics lien under the Sub-contractor’s Lien Law (Sec. 831 GC.), the machine company claims the last item of lumber was an “equipment” rather than a “material” and was therefore not the subject of a lien.

(1) A driveway connecting a garage with the street is a necessary adjunct to the garage. Consequently lumber used on the premises and in the construction of such driveway would be a material rather than an equipment.

(2) A lien in favor of a mechanic will extend to all the materials furnished in good. faith notwithstanding a portion of such materials be directed to a different purpose.

Cite this

Ferro Machine & Foundry Co. v. Willson Ave. Lumber Co., No. 4090 (Ohio Court of Appeals December 18, 1922)

No reporter citation is stored for this case. This line is built from the stored case name, docket number, court and decision date.

The court’s opinion as stored in our database. This is the stored text for research. It is not legal advice; check the official source before you rely on it.