MATTHIAS, J.

1. The provisions of Section 8312, General Code, requiring notice to be served upon the owner of a structure being erected under contract, apply to the contractor and sub-contractor but not to material men.

2. Whether materials furnished by a dealer to a contractor to be used in the process of the erection of a building were selected from the stock of the dealer or made by him in his own establishment or procured from another dealer, having nothing to do relative to the installation of said materials or the fabrication thereof into the structure, is a material man and not a sub-contractor.

3. The provisions of Section 8323, General Code, authorize the payment of an attorney fee only out of the fund realized for lien claimants, which fund is the sum applicable to the payment of mechanics’ lien claims found to be valid.

Jones, Day, Allen, Kinkade and Robinson, JJ., concur. Marshall, CJ.,, concurs in propositions 1 and 2 of the syllabus and in the judgment.

Judgment modified and affirmed.

Cite this

Matzinger v. Harvard Lumber Co., No. 20041 (Ohio Supreme Court July 1, 1926)

No reporter citation is stored for this case. This line is built from the stored case name, docket number, court and decision date.

The court’s opinion as stored in our database. This is the stored text for research. It is not legal advice; check the official source before you rely on it.