Case law · Highest court · Iowa

Davenport v. Wells

Decided
June 15, 1856
Status
Published
Judges
Woodward
Jurisdiction
Iowa

Cited onceNo negative treatment found in this library

What does the opinion say?

Woodward, J.

The rule is, that when the contractor has received the price, he is liable for the highest price between the day of delivery, and either the commencement of suit, or the time of trial, but which of these, it is not necessary now to determine; and as a promissory note or due bill is prima facie evidence of indebtedness, or of having received the price, this case would stand upon that rule. See Cannon v. Folsom, 2 Iowa, 101; Foley v. McKeegan, at the December term, 1855, of this court.

When this cause was before the court at the last term, the statement of facts was ambiguous, and led to the supposition that the tender was made on the 27th of April, the day the due bill was made and was due, in which case the former decision was right.

The judgment of the District Court is affirmed.

Cite this

Davenport v. Wells (Supreme Court of Iowa June 15, 1856)

No reporter citation is stored for this case. This line is built from the stored case name, docket number, court and decision date.

The court’s opinion as stored in our database. This is the stored text for research. It is not legal advice; check the official source before you rely on it.