Paladino Contracting Co. v. Walsh
- Decided
- November 13, 1913
- Status
- Published
- Judges
- Guy
- Jurisdiction
- New York
Cited 0 timesNo negative treatment found in this library
What does the opinion say?
GUY, J.
This action was brought to recover a balance of contract price claimed by plaintiff to be due under a written contract whereby plaintiff agreed to do the excavation of a cellar for a public school for the sum of $4,665, the excavation to be 162 feet in length, 102 feet in width, and 8 feet in depth. The contract made provision for payments during the progress of the work, the balance to be paid 30 days after completion. All but $1,665 was paid, and suit is brought to recover that sum.
While no plans were introduced in evidence, the proof shows that the lines of the excavation were staked out by representatives of plaintiff and defendants in accordance with a survey, which was used by the parties, but was not introduced in evidence on the trial. It is clearly established by the evidence that, instead of excavating as provided by the contract and as staked out by the parties under the contract, viz., 162 feet in length and 102 feet in width, plaintiff only excavated 161 feet in length by 99 feet 8 inches in width, and, when requested to complete the excavation, failed and neglected to do so. The defects complained of are material, and the evidence shows that defendants had to perform a large amount of work to complete the excavation as required by the contract. Defendants did not set up any counterclaim, but defend on the ground of failure to perform. Plaintiff, having failed to show a substantial performance of its contract, is not entitled to recover.
The judgment must therefore be reversed, and a new trial ordered, with costs to appellants to abide the event. All concur.
Cite this
Paladino Contracting Co. v. Walsh (Appellate Terms of the Supreme Court of New York November 13, 1913)No reporter citation is stored for this case. This line is built from the stored case name, docket number, court and decision date.
The court’s opinion as stored in our database. This is the stored text for research. It is not legal advice; check the official source before you rely on it.