Case law · Appeals court · Florida

Shupnick v. Pershing Auto Leasing, Inc.

Decided
October 17, 1978
Docket
No. 77-1193
Status
Published
Judges
Hendry, Kehoe, Pierce, Ret, William
Jurisdiction
Florida

Cited onceNo negative treatment found in this library

What does the opinion say?

PER CURIAM.

Lawrence Shupnick, appellant, here appeals a summary judgment entered for ap-pellee in a breach of contract action.

In 1967, Shupnick entered into an agreement with Pershing Auto Leasing (Pershing). This agreement provided that Pershing supply Shupnick with two new fully insured and serviced Cadillacs per year for his use during the term of the agreement.

Thereafter Pershing became a wholly owned subsidiary of Pershing Industries, Inc., which entered into an agreement on May 14, 1969 with Shupnick. At that time Shupnick signed a release with respect to the 1967 agreement in consideration of Pershing Industries, Inc. entry into the transfer agreement. Nevertheless, the 1969 agreement became the subject matter of ensuing litigation and was rescinded and held to be invalid by the Circuit Court, affirmed by this Court. See Pershing Industries, Inc. v. Shupnick, 325 So.2d 410 (Fla. 3d DCA 1976). Subsequently, Pershing, which had ceased to be a wholly owned subsidiary of Pershing Industries, Inc., failed to furnish Shupnick with the Cad-illacs pursuant to the 1967 agreement and Shupnick filed the present action for breach of this agreement. Following pretrial hearing, Shupnick moved for summary judg [*199] ment. Pershing also filed a motion for summary judgment on the ground that Shupnick had executed in its favor a release with respect to this 1967 agreement, which is the subject of this suit. The Circuit Judge entered summary judgment for Pershing and Shupnick appeals therefrom. We reverse.

Even though the May, 1969 agreement was rescinded and held to be invalid (see Pershing, supra), there was a total failure of consideration for the release, justifying its rescission. See Diesel Heat & Power v. Dixon Marine Indus. Pow. Trans., 232 F.2d 217 (5th Cir. 1956). We therefore conclude that there remain genuine issues of material fact to be resolved with regard to the alleged breach of the 1967 agreement. See Bethlehem Steel Corp. v. Centex Homes Corporation, 327 So.2d 837 (Fla. 3d DCA 1976). Accordingly, the summary judgment is reversed and the cause is remanded to the Circuit Court for further proceedings.

Reversed and remanded.

Cite this

Shupnick v. Pershing Auto Leasing, Inc., No. 77-1193 (District Court of Appeal of Florida October 17, 1978)

No reporter citation is stored for this case. This line is built from the stored case name, docket number, court and decision date.

The court’s opinion as stored in our database. This is the stored text for research. It is not legal advice; check the official source before you rely on it.