Case law · Appeals court · Florida

Westinghouse Electric Corp. v. Williams

Decided
February 18, 1980
Docket
No. QQ-224
Status
Published
Judges
Ervin, Shaw, Shivers
Jurisdiction
Florida

Cited 2 timesNo negative treatment found in this library

What does the opinion say?

PER CURIAM.

The record reveals that the claimant worked for one week in one construction job, and for nine weeks in another construction job during the time he was found to be temporarily totally disabled. The deputy commissioner failed to take cognizance of this evidence in ordering the carrier to:

[Rjeclassify all permanent partial disability benefits paid prior to August 30, 1977, as temporary total disability benefits, . pay to the claimant temporary total disability benefits from the date permanent partial disability benefits terminated until August 30, 1977, .

The order, otherwise affirmed, is reversed as to this award, and the cause is remanded to the deputy commissioner for a new order consistent with this opinion. See MJM Construction Co. v. Roberts, IRC Order 2-3387 (March 31, 1978); Purcell v. Douglas, 8 FCR 375 (1974), cert. denied, 302 So.2d 762 (Fla. 1974).

ERVIN, SHIVERS and SHAW, JJ., concur.

Cite this

Westinghouse Electric Corp. v. Williams, No. QQ-224 (District Court of Appeal of Florida February 18, 1980)

No reporter citation is stored for this case. This line is built from the stored case name, docket number, court and decision date.

The court’s opinion as stored in our database. This is the stored text for research. It is not legal advice; check the official source before you rely on it.