LETTS, Judge.

This bench trial involved a general contractor and a subcontractor as adversaries. We hold that the measure of damages was improper because it was based on a percentage of completion.

The subcontractor was awarded $27,-000.00 predicated on proof of percentage of completion. We recently held that “percentage of completion is not the proper method to prove damages for the breach of a construction contract.” Brooks v. Holsombach, 525 So.2d 910 (Fla. 4th DCA 1988).

Accordingly, we reverse and remand for a new trial on this issue. We affirm the trial court on the matter of the counterclaim.

REVERSED AND REMANDED.

DOWNEY and STONE, JJ., concur.

Cite this

Coutinho Construction, Inc. v. Graph Development, Inc., No. 87-1977 (District Court of Appeal of Florida August 24, 1988)

No reporter citation is stored for this case. This line is built from the stored case name, docket number, court and decision date.

The court’s opinion as stored in our database. This is the stored text for research. It is not legal advice; check the official source before you rely on it.