Case law · Appeals court · Florida

Johnson v. Department of Business & Professional Regulation, Construction Industry Licensing Board

Decided
March 2, 2007
Docket
No. 2D06-1785
Status
Published
Judges
Casanueva, Davis, Edward, Threadgill
Jurisdiction
Florida

Cited 0 timesNo negative treatment found in this library

What does the opinion say?

THREADGILL, EDWARD F., Senior Judge.

Betty Johnson challenges the Department of Business and Professional Regulation Construction Industry Licensing Board’s final order, approving her claim for restitution from the Construction Industries Recovery Fund (“the Fund”)[1] in the amount of $7455. We affirm the approval of Ms. Johnson’s claim; however, because the Board’s final order is internally inconsistent, we reverse as to the amount and remand.

Ms. Johnson’s claim under the Fund stems from a construction contract that she entered into with McDurfee Home Improvement, Inc. Pursuant to the contract and subsequent change orders, Ms. Johnson was to pay McDurfee $28,990 to repair and remodel her pool deck. Ms. Johnson paid an initial deposit of $7455 to McDur-fee. After demolishing the existing deck and patio, McDurfee was unable to meet its obligations under the contract. As such, Ms. Johnson was forced to pay another contractor $85,855 to complete the work.

Under the statute, Ms. Johnson is entitled to restitution in an amount not to exceed $25,000, so long as the amount represents “actual or compensatory damages.” See § 489.143(1). In its order, the Board notes that “actual damages” means the completion cost less the contract price, which includes amounts added pursuant to any subsequent change orders. The Board goes on to approve Ms. Johnson’s claim in the amount of $7455, which [*372] it notes represents the actual damages “calculated by determining the difference between the original contract price after deducting payments to the original contractor, and the total costs incurred by the Claimant to complete the project.”

While we agree with the Board that, under the statute, Ms. Johnson is entitled to actual damages, we disagree with the Board’s arithmetic. Based on the figures that the Board set out in its final order, the difference between the cost of completion ($35,855) and the contract price less any deposits already paid ($28,990-$7455) equals $14,320.

Accordingly, we affirm the Board’s approval of Ms. Johnson’s claim for restitution from the Fund in an amount equal to her actual damages. However, we reverse the award of only $7455 and remand with directions to enter an award in the amount of $14,320.[2]

Affirmed in part, reversed in part, and remanded.

CASANUEVA and DAVIS, JJ., Concur.

[1] . § 489.140, Fla. Stat. (2002).

[2] ^ This amount does not include the $3731.50 in restitution previously awarded to Ms. Johnson by the Board in case no. 2002-004705.

Cite this

Johnson v. Department of Business & Professional Regulation, Construction Industry Licensing Board, No. 2D06-1785 (District Court of Appeal of Florida March 2, 2007)

No reporter citation is stored for this case. This line is built from the stored case name, docket number, court and decision date.

The court’s opinion as stored in our database. This is the stored text for research. It is not legal advice; check the official source before you rely on it.