Barrett v. Department of Highways
- Decided
- September 20, 1979
- Docket
- CC-79-53
- Status
- Published
- Jurisdiction
- West Virginia
Cited 0 timesNo negative treatment found in this library
What does the opinion say?
PER CURIAM:
This claim was submitted upon a duly executed written stipulation to the effect that the respondent is liable for damages in the sum of $68.30, based upon the following facts: On or about December 5,1978, a work crew from the West Virginia Department of Highways was performing work on West Virginia Route 50/9 in the vicinity of the claimant’s residence. In the course of this work, said crew negligently operated a bush hog and broke claimant’s gas line. As this negligence was the proximate cause of the damage suffered by the claimant, the Court finds the respondent liable, and hereby makes an award to the claimant in the amount stipulated.
Award of $68.30.
Cite this
Barrett v. Department of Highways, No. CC-79-53 (West Virginia Court of Claims September 20, 1979)No reporter citation is stored for this case. This line is built from the stored case name, docket number, court and decision date.
The court’s opinion as stored in our database. This is the stored text for research. It is not legal advice; check the official source before you rely on it.