United States v. Peck
- Decided
- March 22, 1880
- Docket
- 788
- Status
- Published
- Judges
- Bradley
- Jurisdiction
- Federal
Cited 108 timesNo negative treatment found in this library
What later courts said
- holding that defendant was excused for contractual nonperformance where plaintiff prevented his performance — Amoco Oil Co. v. Gomez (2000)
- applying these fundamental principles of equity against the government as a party to a contract with a private individual — Barry I. Fredericks v. Commissioner of Internal Revenue (1997)
- applying fundamental principles of equity against the government as a party to a contract — United States v. City of Tacoma, Washington (2003)
Each line is a later court’s own words about this case, not a summary. Read the opinion before relying on it.
What does the opinion say?
Mr. Justice Bradley, after stating the case, delivered the opinion of the court.
We think that the facts of' the case clearly bring it within the rules allowing the introduction of parol evidence: first, for the purpose of showing, by the surrounding circumstances, tbe subject-matter of the contract, namely, hay to be cut and gathered in the region where it was to be delivered; secondly, for the purpose of showing the conduct of the agents of the defendants by which the claimant was encouraged and led on -to rely on a particular means of fulfilling his contract until it was too late to perform it in any other way; and then Avas prevented by these agents themselves from employing those means. The supply of hay Avh,ich he depended on, and which under the circumstances he had a. right to depend ón, Avas taken aAvay by the defendants themselves. In other Avords,- the defendants prevented and hindered the claimant from performing his part of the contract;
That the subject-matter of a contract may be shown by parol evidence of 'the surrounding circumstances, see Bradley v. Washington, Alexandria, & Georgetown Steam Packet Co., 18 Pet. 89;
Thorington v. Smith, 8 Wall. 1;
Maryland v. Railroad Company, 22 id. 105;
Reed v. Insurance Company, 95 U. S. 23; 1 Greenl. Evid., sect. 277; Taylor, Evid., sect. 1082. And that the conduct of one party to a contract which prevents the other from performing his part is an excuse for non-performance, see Addison, Contracts, sect. 326 ;
Fleming v. Gilbert, 3 Johns. (N. Y.) 527. In the case last cited, the defendant Avas sued on a bond obliging him by a certain time to procure and cancel a mortgage of the plaintiff and deliver the same to him. The. defendant was allowed to prove by parol that he procured the mortgage, and, having inquired of the plaintiff what he should do with it, Avas directed to place it in the hands of a third person. . This was held t'o be an excuse for not having fully performed the condition. Judge Thompson said: “ It is. a sound principle that he who prevents a thing being done shall not avail himself of the non-performance he has occa [*66] sioned. Had not the plaintiff dispensed with a further com.pliance with the condition of the bond, it is probable that the defendant would have taken measures to ascertain what steps were requisite to get the mortgage discharged of record, and would have literally complied with the condition of the bond.” So when A. gave to B. a bond to convey certain■ premises, but they subsequently agreed by parol to rescind the contract, and A. thereupon sold the premises to a third person, it was held that though the bond was not cancelled or given up, nor any of the papers changed, yet by the parol agreement and the acts of the parties under' it the bond was discharged.
Dearborn v. Cross, Cow. (N. Y.) 48; and see 2 Cowen & Hill’s Notes to Phillips on Evid., 605. The principle involved in these cases is applicable to the present.
Judgment affirmed.
Note. — The other points involved in the foregoing case were of minor importance, and, at the suggestion1 of the justice who delivered the opinion, are omitted.
Cite this
United States v. Peck, No. 788 (Supreme Court of the United States March 22, 1880)No reporter citation is stored for this case. This line is built from the stored case name, docket number, court and decision date.
The court’s opinion as stored in our database. This is the stored text for research. It is not legal advice; check the official source before you rely on it.